The objective of this audit was to assess the effectiveness of the Australian Government Reconstruction Inspectorate, supported by the National Disaster Recovery Taskforce, in providing assurance that value for money is being achieved in recovery and reconstruction expenditure in Victoria.

Entity
Department of Regional Australia, Local Government, Arts and Sport
Published: Wednesday 8 May 2013
Published

The objective of the audit was to assess the effectiveness of the Tax Practitioners Board's implementation and administration of the regulatory arrangements for tax practitioners under the Tax Agent Services Act 2009.

Entity
Australian Taxation Office; Tax Practitioners Board
Contact

Please direct enquiries relating to reports through our contact page.

Published: Tuesday 18 May 2010
Published

The objective of the audit was to review and assess the use, and management of, automatic exchanges of information under Double Taxation Agreements (DTAs) by the Tax Office.

Entity
Australian Taxation Office
Published: Thursday 17 September 2009
Published

The audit objective was to assess DoHA's administration of prudential arrangements for the protection of residential aged care accommodation bonds.

Entity
Department of Health and Ageing
Published: Thursday 5 November 2009
Published

The objective of the follow-up audit was to assess the extent to which Airservices Australia, and where relevant, the Department of Infrastructure, Transport, Regional Development and Local Government (DITRDLG), have implemented the four ANAO recommendations contained in the previous audit report.

Entity
Airservices Australia; Department of Infrastructure, Transport, Regional Development and Local Government
Responded: Wednesday 23 September 2015
Response provided

The Auditor-General (A/g) responded on 23 September 2015 to correspondence from Ms Julie Collins MP on 1 September 2015 regarding parliamentary entitlements paid to Liberal MPs and Senators.

Contact

Please direct enquiries relating to requests for audit through our contact page.

Published: Tuesday 23 June 2009
Published

The objective of this audit was to assess whether selected organisations had effective security risk management programs, including whether a selection of protective security risk treatment controls was working as designed.

Entity
Across Agencies
Published: Thursday 11 August 2005
Published

The audit objective was to examine whether Health's financial management framework and processes adequately support Health's Secretary, Executive and managers to make informed decisions on the use of Commonwealth resources.

Entity
Department of Health and Ageing
Published: Thursday 8 December 2011
Published

The objective of the audit was to assess the effectiveness of the ATO’s compliance management approach in the SME market.

Entity
Australian Taxation Office
Published: Thursday 27 November 2008
Published

This first Assurance Report on the status of selected Defence equipment acquisition projects, which has the support of the Parliament and the Government, represents a substantial step towards improving transparency and public accountability in major Defence procurement projects. It is the pilot of an annual Defence Materiel Organisation (DMO) Major Projects Report, and was developed in conjunction with the DMO. It covers the cost, schedule and capability progress achieved by nine DMO projects, which had an approved budget totalling $13.535 billion as at 30 June 2008.

This report is organised into three parts. Part 1 comprises an ANAO overview and Auditor–General's Foreword. Part 2 comprises the Major Projects Report prepared by DMO, including an overview reflecting DMO's perspective on their business and on the nine projects included in the. Part 3 incorporates the Auditor-General's Review Report, the statement by the CEO DMO, and the information prepared by DMO in the form of standardised Project Data Summary Sheets covering each of the nine pilot projects.

In the next 12 months, the ANAO will review 15 DMO projects planned for inclusion in the 2008-09 DMO Major Projects Report, with the number of projects rising to 30 projects in subsequent years. The ANAO will also work with DMO to refine the approach adopted for providing assurance on each project's progress toward achieving Final Operational Capability. The ANAO will also consider the inclusion of an analysis of each project's emerging trends, as appropriate, to complement DMO's intention to provide improved analysis of project management performance regarding all projects included in the Major Projects Report.

Entity
Defence Materiel Organisation